Procurement Route Pros & Cons
Contents |
[edit] Traditional Procurement
Good for:
- QUALITY – full design pre tender
- DESIGN FLEXIBILITY – variations & instructions
- SPECIALIST SUB-CON’S – Named specialist update sbc11
- DESIGN CONTROL – through arch/CA
- CDPs – eg. M&E
- COMPLEX
- COST – lump sum cost benefits unless multiple changes made
Not Suited for:
- TIME – req full detailed pack pre tender
- COST – not a benefit if many changes made
- INCOMPLETE DRAWINGS – lead to delay, costs and claims of negligence
Contract: SBC11
- LUMP SUM PAYMENT
- CDM
- CDP’s
- NAMED SUB CONTRACTORS
- VARIATIONS/INSTRUCTIONS
- RETENTION
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- PREAGREED ALT DISPUTE RESOLUTION
[edit] D&B Procurement
Good for:
- TIME – Fast track, overlap design & construction
- COST – lump sum/ GMP
- SINGLE POINT RESPONSIBILITY – Contractor design and build responsibility
- COMPLEX
- NOVATION – can benefit quality. Prior knowledge, sub-con drawing review
- CLIENT RISK LOW
- NAMED SUB-CON – in employers requirements
Not suited for:
- QUALITY – cheapest route to meet contract spec can lead to low quality products/ build quality.
- DESIGN FLEXIBILITY – request for change – costs/time implications
Contract: DB11
- CONTRACTOR TO COMPLETE DESIGN +CARRY OUT WORKS
- LUMP SUM/GMP
- CDM
- COLLATERAL WARRANTIES
- TERMINATION PROVISIONS
- RETENTION
- PRE AGREED DISPUTE RESOLUTION
[edit] Management Contracting Procurement
Good for:
- COMPLEX/SPECIALIST – individually appointed packages to best suited sub-contractor
- POTENTIAL COST SAVING – Competitive tender
- TIME – Overlap design/construction
- QUALITY – each package subcontracted to specialist
- DESIGN FLEXIBILITY – changes can be made throughout construction. Potential costs.
Not suited for:
- INEXPERIENCED – risk high
- FIXED COST - Prime cost basis per package. Fluctuations.
- LACK OF AVAILABLE SPECIALISTS – would leave gaps in work to be undertaken.
Contract: MC11
- PRIME COST CONTRACT
- PROVISIONS FOR COLLATERAL WARRANTIES
- SUSTAINABILITY
- COLLABERATIVE WORKING
- THIRD PARTY RIGHTS – funder-contractor
[edit] Construction Management Procurement
Good for:
- COMPLEX/SPECIALIST - individually appointed packages to best suited sub-contractor
- TIME - Overlap design/construction
- DESIGN FLEXIBILITY - changes can be made throughout construction. Potential costs.
- POTENTIAL COST SAVING - Competitive tender
- QUALITY - each package subcontracted to specialist
- ALL BUILDING TYPES
- EFFICIENCY – Early appointment of CM to aid programme
Not suited for:
- UNEXPERIENCED EMPLOYER – risk high as appointing trade contractors
- FIXED COST- Prime cost basis per package.
- LACK OF AVAILABLE SPECIALISTS
Contracts:
CM/TC11
CM/A
- EMPLYER – CM
- COLLATERAL WARRANTIES
- SUSTAINABILITY
Featured articles and news
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.